Project description

The existing hydrogen laboratory in building E at the Rüsselsheim campus is in poor structural condition and is to be replaced by a new energy storage laboratory. As part of this development, research activities will be expanded through innovative research facilities. The new building is to be constructed on an existing parking lot on August-Bebel-Strasse, in close proximity to the current building. Once the new facility has been completed, building E is to be demolished and the cleared area will be redesigned as part of the outdoor facilities.
The new building for the Department of Engineering will comprise an energy storage laboratory, including a hydrogen / fuel cell laboratory and a battery laboratory.
LOGO is responsible for project management and requirements planning. In this context, LOGO prepares cost estimates based on cost area categories (KFA), including the determination of special costs, a preliminary project schedule, and the documentation in accordance with GA-Bau Form 13 with all necessary adjustments. These documents are required for the budgetary approval of the construction project.


Customer

RheinMain University of Applied Sciences, Wiesbaden, Germany


Services

  • Project management services in accordance with AHO No. 9, project stage 1, action areas A–D, cost groups 300–400
  • Cost estimate based on cost area categories (KFA), taking into account the HIS-HE report on the requirements analysis and the resulting space program
  • Determination of special costs
  • Preparation of a preliminary project schedule, including all required modifications
  • Preparation of documentation in accordance with GA-Bau Form 13, including all required modifications

Project data

  • Project period: July 2025 to September 2025
  • Total usable area (NUF 1–6): 1,200 m²
  • Construction costs (cost group 300–400): approx. EUR 17 million
  • Total costs: approx. EUR 35 million