Project

Operational Reliability at the Berlin-Tegel and Berlin Schönefeld Airports

Berlin,
Germany

Project description

Due to the enormous increase in passenger figures, the existing passenger terminals have reached their capacity limits. Their operability needs to be ensured and optimized until the new Berlin Brandenburg Airport (BER) is put into operation. To ensure and optimize flight and terminal operations, a total of 140 individual measures were coordinated and implemented in the terminal buildings and apron areas. LOGO InfraConsult handled the
multi-project management geared towards ensuring economic and technical control of the construction measures implemented at the Berlin-Tegel and Berlin Schönefeld Airports.

Customer

Flughafen Berlin Brandenburg GmbH,
Department: Operation 

Services

  • Multi-project management
  • Project communication and flow of information
  • Organization of meetings and reporting
  • Cost and budget planning / controlling
  • Change management
  • Scheduling and deadline control
  • Risk management
  • User and demand planning
  • Documentation

Project data

  • 140 individual measures
  • 10 subprojects
  • Terminal, aviation areas, baggage, security, IT infrastructure, supply and disposal
  • Investment volume: EUR 20 million
  • Project period: 06/2013 - 08/2014