Project description
In order to prepare the commissioning of the aviation areas of the new Berlin Brandenburg Airport (BER), it was necessary to refurbish the existing runway (07L/25R) North at Berlin Schönefeld Airport (SXF). During the refurbishment of the North runway, parts of the BER infrastructure, in particular the South runway (07R/25L) and the south taxiways had to be used temporarily to ensure consistent flight operations. LOGO InfraConsult was responsible for the operational project management during execution of the construction activities.
Customer
Flughafen Berlin Brandenburg GmbH,
Department: Aviation
Services
- Project communication and flow of information
- Organization of meetings and reporting
- Cost and budget planning / controlling
- Change management
- Scheduling and deadline control
- Risk management
- Coordination of the clients’ interests
- Coordination of individual measures of the task packages
- Implementation management during the construction phase
- Documentation
Project data
- Refurbishment of the runway (07L/25R) North, 3,600 m; incl. the corresponding safety areas (runway strip / RESA)
- Temporary start-up of the South runway
- Individual measures, incl. apron services, security, area surfaces, fire department, technical retrofitting
- Investment volume: approx. EUR 50 million
- Project period 02/2014 - 12/2015