Project description

LOGO has been supporting the new concept of the third passenger terminal, located in the area of the former US-Air Base in Frankfurt since 2012 . A superordinated, database-supported requirements management compiles the complex space and functions specifications which will be further-detailed during the course of the planning progress. Quality management by LOGO InfraConsult will ensure the implementation of planned processes, space requirements as well as technical equipment required for passenger and baggage services.

Customer

Fraport Ausbau Süd GmbH,
Department: Fraport AG, Central Infrastructure Management

 

Services

  • Preparation of binding planning specifications and targets (requirements management)
  • Function-oriented conceptual studies
  • Depiction and assessment of planning options
  • Target monitoring (design review)
  • Database-supported project management
  • Coordination of operational issues
  • Coordination of the technical equipment for passenger services and safety
  • Stakeholder management

Project data

  • Capacity up to 25 million passengers per year
  • 75 aircraft positions
  • Area ca. 400.000 m²
  • New infrastructure connection
  • Total investment of approx. EUR 2.5 billion
  • Commissioning target date 2026
  • Project start 2012