Project description

As part of the “HAM2020” program, Flughafen Hamburg GmbH is expanding the airport’s South Pier in order to handle the constant increase in passenger volumes. Some gates will need to be decommissioned during the construction measures, which means that a temporary shuttle gate will have to be built at ramp 2 to ensure efficient and smooth airport processes. Just like other projects implemented at Hamburg Airport, LOGO InfraConsult GmbH supports the planning with database-driven requirements management.

Customer

Flughafen Hamburg GmbH,
Department: Structural Engineering

Services

  • Requirements analysis
  • Development of binding plans and objectives (requirements management)
  • Coordination of operational issues
  • Coordination of technical equipment for passenger handling and airport security
  • Support in project management
  • Documentation management

Project data

  • Temporary terminal with short realization period
  • 14 gates
  • Total area: approx. 8,000 m2
  • Construction costs: approx. EUR 30 million
  • Project start: 2017; commissioning target date: 2019